OBJECTIVES


Execution of plant dismantling and transformation work.

CLIENT REQUEST


The refinery has embarked on a major transformation to become a zero-oil platform, aligned with carbon neutrality objectives.

The project requires investments of over €500 million to develop four new industrial activities, including biofuel and bioplastics production, plastics recycling and the operation of solar photovoltaic power plants.

CHALLENGE


The refinery ceased operations, leading to a steam supply interruption. To avoid any delays in the plant’s dismantling and redevelopment process, our client and their chemical treatment specialist partner sought a modular, fast, and energy-independent solution.

TIBBLOC SOLUTION


Tibbloc deployed three steam boilers, each with a capacity of 3 T/h, 6 T/h, and 10 T/h.

Equipped with food-grade tarpaulins, discharge valves, softeners, and fuel tanks, these boilers are interconnected at multiple injection points, ensuring the necessary steam for efficient chemical propulsion.

PROFITS


Tibbloc your your partner for complex refinery needs

OBJECTIVES


To meet a steam requirement for a car battery factory and supply 25 T/h of steam while treating effluents before their discharge into the environment.

CLIENT REQUEST


In its production line, the factory uses steam and is investing in boiler rooms: 2x 25 T/h gas-fired and 1x 25 T/h electric.

We intervene upstream of production to assist with the factory’s startup while awaiting the full delivery of the permanent boiler room.

CHALLENGE


TIBBLOC SOLUTION


Multi-stage deployment:

Accessories:

Steam and condensate manifold | MID energy meters | Effluent treatment | Steam valve | Gas valve

PROFITS