20 July 2026

Critical Industrial Process Cooling

OBJECTIVES

Combining cooling power and energy eco-efficiency for sensitive processes during periods of high heat.


CLIENT REQUEST

As part of the process security plan during the summer period, it is necessary to be able to cool installations including compressors and heat pumps with high-performance, energy-efficient, and proven cooling systems.


CHALLENGE

  • To have, during a heatwave (outside temperature >35 °C), supplementary cooling capacity.

    • 1,700 kW to lower the process temperature to 27 °C, which is 10 °C compared to the water inlet temperature.
    • 4,400 kW to lower the process temperature to 30 °C, which is 25 °C compared to the water inlet temperature.

TIBBLOC SOLUTION

A combination of several proven technologies:


PROFITS

  • Compliance with the required temperature regime
  • Reduced water consumption
  • Low energy consumption
  • Compliance with current regulations
  • Maintenance of production in case of cooling circuit malfunction.