For a leading steel company, implementation of a 7MW+ hot power solution in a temporary boiler room within one week

We also supply and install 1.2MW of heaters, 12 air handling units of 20,000m3/h with 280m of ventilation ducts in diameter 500 and 1.8Km of hoses (DN80 and DN50).

This turnkey service involved 6 Tibbloc technicians, 12 flatbed trucks and 1 crane.

The installation is now operational and we would like to thank all our teams, who, once again, have made it possible to meet the deadlines and fully satisfy our Client.