For a leading steel company, implementation of a 7MW+ hot power solution in a temporary boiler room within one week

We also supply and install 1.2MW of heaters, 12 air handling units of 20,000m3/h with 280m of ventilation ducts in diameter 500 and 1.8Km of hoses (DN80 and DN50).

This turnkey service involved 6 Tibbloc technicians, 12 flatbed trucks and 1 crane.

The installation is now operational and we would like to thank all our teams, who, once again, have made it possible to meet the deadlines and fully satisfy our Client.

Installation of a boiler room and an air handling unit in an 8000m2 production hall.

It is a turnkey offer, with remote monitoring of the installations and regular maintenance.