Early Production Start-Up
Context
During the creation of a gigafactory, a steam supply of up to 25 tons/hour was required to ensure:
- Building heating
- Precise humidity control, particularly in battery areas sensitive to moisture
This solution had to be operational before the permanent boiler room was commissioned.
Tibbloc Solution
- Progressive deployment of 4 steam boilers (1 T/h, 6 T/h, 10 T/h, 16 T/h)
- Temporary steam production
- Water treatment and softening
- Steam feedwater tanks and distribution network
- Gradual capacity ramp-up from 1.3 T/h to 25 T/h
Project duration: 10 months
Result:
Early production start-up, before completion of the permanent boiler room, generating immediate value for the client.